When called upon by a major customer to assist them with a very short construction lead time, Khansaheb Sykes rose to the challenge and actioned a dewatering solution for the construction of a 3km long ‘pipe line trench’.

Khansaheb Sykes immediately mobilised 15 x Dewatering Pumps along with the essential dewatering accessories to complete this challenge in Abu Dhabi.

The solution was to dewater this 3km trench using a conventional Wellpoint Dewatering System, thereby enabling the client to complete their tasks of constructing and installing the Chiller Pipe for the new build of an IKEA Store on the prestigious Yas Island Development.

Mobile well pointing solution – in advance of laying the 3km pipeline on the prestigious Yas Island Development.
Mobile well pointing solution – in advance of laying the 3km pipeline on the prestigious Yas Island Development.

Khansaheb Sykes’s expertise within the Dewatering sector again proved our reliability in delivering dewatering solutions on time, with special thanks being gratefully received from Mr Abdul Hadi, Project Manager of Bin Darwish Gen. Cont. & Maint. Est:

“I want to convey a special thanks to you and all your team members for your dedication and effort to achieve the target on time”.

For more information on Deep Well Dewatering or Ground Water Control services:
Call our Toll free 800 SYKES number, email us, or visit our Middle Eastern web site: